Warm Temperate Biome23/04/01 Plants waiting to go in to Warm 08/05/01 taken from the Arena
19/10/10 21/03/01
07/01/01 Warm steamed up with the heat inside. More trees planted along the bank. 30/12/00 The warm biome looking like three igloos in the Artic 10.45 am
29/12/00 21/12/00 Pathways being laid for access to the biomes.
13/12/00 Warm biome get louvered vents adjusted. 25/11/00 Warm biome - louvered air vents in place. Warm biome gets final touches. 06/11/00 Warm biome in a sunny spot 16/11/00 Warm from the land train.
01/11/00 All action at the warm biome, lunch time action anyway.
30/10/00 Vents and heat exchangers are looking fine. No problem with 90mph winds last night
25/10/00 Work installing the heat exchangers and door way/vents
17/10/00 Doors being sealed to test heating. 25/10/00 Insulation being installed
11/10/00 17/10/00
04/10/00
03/10/00 Getting ready for planting.
26/09/00 Soil going into the warm biome planting will start soon.
19/09/00 Tree/Shrubs planting 22/09/00
11/09/00
08/09/00 Soil going in by the load 11/09/00 Land train view of the warm biome
05/09/00 2.00 pm
Warm biome on 04/09/00 11.00 am
Last of the roof panels going in 22/08/00
14/08/00 14/08/00
09/08/00 11/08/00
07/08/00 09/08/00
06/08/00 07/08/00
03/08/00 03/08/00
31/07/00 31/07/00
28/07/00 28/07/00
24/07/00 24/07/00
16/07/00 18/07/00
07/07/00 11/07/00
04/07/00 04/07/00
28/06/00 28/06/00
26/06/00 26/06/00
26/06/00
24/06/00 24/06/00
05/06/00 20/06/00
|